74.5 MW generation in Putnam, FL · In queue since July 2020 · Proposed COD July 2030
74.5 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
10 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-07-31
The proposed FPL-398 project is a 74.5 MW solar generation project located in Putnam County, Florida. The developer is Florida Power & Light (FPL). It is an active project in the queue of the utility Florida Power & Light, with a queue entry date of July 21, 2020.
The proposed commercial operation date (COD) for the project is July 31, 2030. Its interconnection agreement (IA) status is currently in the Facility Study phase. The point of interconnection (POI) is Carter-Duval.
Generated from interconnection queue and public data sources
State
FL
County
Putnam
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Carter-Duval
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.