FPL-403
74.5 MW generation in St. Lucie, FL · In queue since July 2020 · Proposed COD January 2025
74.5 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
4y 6m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-31
FPL-403 is a proposed solar generation project located in St. Lucie County, Florida, with a total capacity of 74.5 MW. The developer is Florida Power & Light (FPL). The project is interconnected to the Florida Power & Light system at the Sweatt Substation.
The project entered the Florida Reliability Coordinating Council (FRCC) interconnection queue on July 21, 2020, and has a proposed commercial operation date of January 31, 2025. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
St. Lucie
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Sweatt Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-403