FPL-413
74.5 MW generation in Desoto, FL · In queue since July 2020 · Proposed COD April 2027
74.5 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-30
FPL-413 is a proposed 74.5 MW solar generation project located in Desoto County, Florida. The project, developed by Florida Power & Light (FPL), is in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of July 21, 2020. The proposed commercial operation date is April 30, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Bermont Substation.
Generated from interconnection queue and public data sources
State
FL
County
Desoto
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Bermont Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-413