FPL-414
74.5 MW generation in Desoto, FL · In queue since July 2020 · Proposed COD January 2029
74.5 MW
Capacity
1
Components
Solar
5y 10m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-31
FPL-414 is a proposed solar generation project with a total capacity of 74.5 MW, located in Desoto County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Power & Light utility grid at the Bermont Substation.
The project is currently in the Facility Study phase of the Florida Reliability Coordinating Council (FRCC) interconnection queue, with a queue entry date of July 21, 2020, and a proposed commercial operation date of January 31, 2029.
Generated from interconnection queue and public data sources
State
FL
County
Desoto
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Bermont Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.