FPL-415
87 MW generation in Manatee, FL · In queue since September 2020 · Proposed COD December 2026
87 MW
Capacity
1
Components
Gas
5y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
FPL-415 is a proposed 87 MW gas-fired generation project located in Manatee County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected within the Florida Power & Light utility territory. It entered the interconnection queue on September 14, 2020, and has a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 87 MW of gas-fired generation capacity. It is listed in the interconnection queue as FPL-415.
Generated from interconnection queue and public data sources
State
FL
County
Manatee
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Manatee Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.