Project FPL-415 — Project Summary

Queue ID
FPL-415
Capacity
87 MW
Technology
Gas
Status
active
Location
Manatee, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

FPL-415

FPL-415BetaActiveGasFPLLBNL

87 MW generation in Manatee, FL · In queue since September 2020 · Proposed COD December 2026

87 MW

Capacity

1

Components

Gas

5y 8m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

6y 3m

Facilities Study50%
Queue EntrySep 14, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

About

FPL-415 is a proposed 87 MW gas-fired generation project located in Manatee County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected within the Florida Power & Light utility territory. It entered the interconnection queue on September 14, 2020, and has a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase.

The proposed project consists of 87 MW of gas-fired generation capacity. It is listed in the interconnection queue as FPL-415.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Manatee

Grid Region

Southeast

Market

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Service Type

Point of Interconnection

Manatee Sub

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project FPL-415