Project FPL-422 — Project Summary

Queue ID
FPL-422
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Manatee, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

FPL-422

FPL-422BetaActiveSolarFPLLBNL

74.5 MW generation in Manatee, FL · In queue since May 2021 · Proposed COD January 2025

74.5 MW

Capacity

1

Components

Solar

5 years

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection

Total Duration

3y 8m

Schedule

15 months past proposed COD

Facilities Study50%
Queue EntryMay 11, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-01-31

About

The proposed project FPL-422 is a 74.5 MW solar generation project located in Manatee County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Florida Power & Light system via the Coachwhip-Sunshine point of interconnection.

This project is listed in the Florida Reliability Coordinating Council (FRCC) interconnection queue as of May 11, 2021, with a proposed commercial operation date of January 31, 2025. Its interconnection status is currently in the Facility Study phase. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Manatee

Grid Region

Southeast

Market

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Service Type

Point of Interconnection

Coachwhip-Sunshine

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project FPL-422