FPL-424A
74.5 MW generation in Leon, FL · In queue since August 2021 · Proposed COD July 2028
74.5 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
FPL-424A is a proposed solar generation project located in Leon County, Florida, with a total capacity of 74.5 MW. The developer is Florida Power & Light (FPL). This project is currently active in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of August 5, 2021. The proposed commercial operation date is July 31, 2028. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the Raven - Sinai 161kV line.
The proposed project consists of 74.5 MW of solar photovoltaic generation. It is sponsored by Florida Power & Light, the local utility. The project has appeared in recent news coverage regarding FPL's renewable energy development plans in the state.
Generated from interconnection queue and public data sources
State
FL
County
Leon
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Raven - Sinai 161kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.