FPL-424C
74.5 MW generation in Madison, FL · In queue since August 2021 · Proposed COD December 2024
74.5 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
3y 4m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
FPL-424C is a proposed solar generation project with a total capacity of 74.5 MW, located in Madison County, Florida. The developer and utility are both Florida Power & Light (FPL). This project is in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of August 5, 2021, and a proposed commercial operation date of December 31, 2024. The project's interconnection status is currently in the Facility Study phase, and its point of interconnection is the Raven - Sinai 161kV line.
This development project consists of 74.5 MW of solar photovoltaic generation. Recent news coverage has discussed this project.
Generated from interconnection queue and public data sources
State
FL
County
Madison
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Raven - Sinai 161kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-424C