Project FPL-424D — Project Summary

Queue ID
FPL-424D
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Madison, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

FPL-424D

FPL-424DBetaActiveSolarFPLLBNL

74.5 MW generation in Madison, FL · In queue since August 2021 · Proposed COD April 2027

74.5 MW

Capacity

1

Components

Solar

4y 9m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

5y 8m

Facilities Study50%
Queue EntryAug 5, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-30

About

The proposed project FPL-424D is a 74.5 MW solar generation project located in Madison County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Raven - Sinai 161kV line.

The project is in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of August 5, 2021. Its proposed commercial operation date is April 30, 2027. The project's interconnection status is currently in the Facility Study phase.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Madison

Grid Region

Southeast

Market

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Service Type

Point of Interconnection

Raven - Sinai 161kV line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.