FPL-425
74.9 MW hybrid in Bradford, FL · In queue since August 2021 · Proposed COD June 2027
74.9 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-25
The proposed project FPL-425 is a 74.9 MW solar and battery hybrid development in Bradford County, Florida. The project, being developed by a third party, is located within the Florida Power & Light (FPL) service area in the Southeast region. It consists of 74.9 MW of solar capacity.
The project is currently active in the FPL interconnection queue with an entry date of August 20, 2021. The proposed commercial operation date is June 25, 2027. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is Deerhaven (GVL)-Bradford 138kV.
Generated from interconnection queue and public data sources
State
FL
County
Bradford
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Deerhaven (GVL)-Bradford 138kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.