FPL-425A
75 MW hybrid in Jackson, FL · In queue since February 2022 · Proposed COD March 2029
75 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-01
The proposed FPL-425A project is a 75 MW solar and battery hybrid development in Jackson County, Florida. The project, being developed by a third party, consists of 75 MW of solar generation. It is interconnected to the Florida Power & Light (FPL) system at the Holmes Creek-Highlands City 230kV point of interconnection.
The project is currently in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of February 7, 2022. Its proposed commercial operation date is March 1, 2029, and the project is currently in the Facility Study phase of the interconnection process.
Generated from interconnection queue and public data sources
State
FL
County
Jackson
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Holmes Creek-Highlands City 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-425A