FPL-425B
74.5 MW generation in Gadsden, FL · In queue since February 2022 · Proposed COD July 2028
74.5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
FPL-425B is a proposed 74.5 MW solar generation project located in Gadsden County, Florida. The developer is Florida Power & Light (FPL). The project is interconnected to the Florida Power & Light system via the Raven - Sinai 161kV line.
The project is listed in the Florida Reliability Coordinating Council (FRCC) interconnection queue with an entry date of February 15, 2022. Its proposed commercial operation date is July 31, 2028, and its interconnection agreement status is currently in the Facility Study phase. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Gadsden
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Raven - Sinai 161kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.