FPL-426
24.5 MW generation in Miami-Dade, FL · In queue since February 2022 · Proposed COD January 2025
24.5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
2y 11m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-31
FPL-426 is a proposed solar generation project with a total capacity of 24.5 MW, located in Miami-Dade County, Florida. The developer and interconnecting utility is Florida Power & Light (FPL). The project is actively listed in the queue of the Southeast region, with an interconnection queue entry date of February 25, 2022, and a proposed commercial operation date of January 31, 2025. Its interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is the Davis-Florida City #2 138kV substation. Recent news coverage has discussed this development project.
Generated from interconnection queue and public data sources
State
FL
County
Miami-Dade
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Davis-Florida City #2 138kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-426