FPL-429
74.5 MW generation in Desoto, FL · In queue since March 2022 · Proposed COD April 2027
74.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-30
The proposed FPL-429 project is a 74.5 MW solar generation facility located in Desoto County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Reliability Coordinating Council (FRCC) queue. It entered the queue on March 2, 2022, with a proposed commercial operation date of April 30, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 74.5 MW of solar photovoltaic generation. It is interconnected at the Orange River-Whidden 230kV point of interconnection. The project has appeared in recent news coverage regarding FPL's renewable energy expansion plans.
Generated from interconnection queue and public data sources
State
FL
County
Desoto
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Orange River-Whidden 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.