FPL-432
74.5 MW generation in Indian River, FL · In queue since March 2022 · Proposed COD October 2027
74.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
The proposed project FPL-432 is a 74.5 MW solar generation project located in Indian River County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Kiran-Eldora 230kV point of interconnection.
The project is in the queue of Florida Power & Light with a queue entry date of March 2, 2022, and a proposed commercial operation date of October 31, 2027. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Indian River
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Kiran-Eldora 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-432