FPL-433
74.5 MW generation in Manatee, FL · In queue since March 2022 · Proposed COD July 2029
74.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
FPL-433 is a proposed solar generation project located in Manatee County, Florida, with a total capacity of 74.5 MW. The developer is Florida Power & Light (FPL). The project is currently active in the Florida Power & Light interconnection queue, with an entry date of March 2, 2022, and a proposed commercial operation date of July 31, 2029. Its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 74.5 MW of solar photovoltaic generation. The point of interconnection is the Coachwhip-Sunshine node. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Manatee
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Coachwhip-Sunshine
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.