FPL-434
74.5 MW generation in Desoto, FL · In queue since March 2022 · Proposed COD October 2027
74.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
FPL-434 is a proposed solar generation project with a total capacity of 74.5 MW. The development is located in Desoto County, Florida, within the Southeast region, and is being developed by Florida Power & Light (FPL). The project entered the Florida Power & Light interconnection queue on March 2, 2022, with a proposed commercial operation date of October 31, 2027. Its interconnection status is currently in the Facility Study phase.
The proposed project consists of 74.5 MW of solar generation. The point of interconnection is the Whidden Substation.
Generated from interconnection queue and public data sources
State
FL
County
Desoto
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Whidden Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-434