FPL-438
74.5 MW generation in Hendry, FL · In queue since March 2022 · Proposed COD July 2028
74.5 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
The proposed FPL-438 project is a 74.5 MW solar generation facility in Hendry County, Florida. The project, being developed by Florida Power & Light (FPL), is located in the Southeast region and is interconnected with Florida Power & Light. It entered the interconnection queue on March 2, 2022, with a proposed commercial operation date of July 31, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 74.5 MW of solar photovoltaic generation. The point of interconnection is the South Bay-Alva substation. The project has appeared in recent news coverage regarding FPL's renewable energy development plans.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
South Bay-Alva
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-438