FPL-445
74.5 MW generation in St. Lucie, FL · In queue since April 2022 · Proposed COD January 2028
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-31
The proposed project FPL-445 is a 74.5 MW solar generation project located in St. Lucie County, Florida. The developer and utility are both Florida Power & Light (FPL). This project is actively listed in the queue of an ISO/RTO in the Southeast region, with a queue entry date of April 6, 2022, and a proposed commercial operation date of January 31, 2028. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection (POI) for the project is Northern St. Lucie County. Recent news coverage has discussed this development project.
Generated from interconnection queue and public data sources
State
FL
County
St. Lucie
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Northern St. Lucie County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.