FPL-447
74.5 MW generation in St. Lucie, FL · In queue since April 2022 · Proposed COD January 2027
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-31
FPL-447 is a proposed solar generation project located in St. Lucie County, Florida, with a total capacity of 74.5 MW. The project, being developed by Florida Power & Light (FPL), entered the Florida Power & Light (FPL) interconnection queue on April 6, 2022. Its proposed commercial operation date is January 31, 2027. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is Northern St. Lucie County.
The proposed project consists of 74.5 MW of solar photovoltaic generation. It is located in the Southeast region of the United States. The project has appeared in recent news coverage regarding FPL's renewable energy development plans.
Generated from interconnection queue and public data sources
State
FL
County
St. Lucie
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Northern St. Lucie County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.