FPL-449
74.5 MW generation in St. Lucie, FL · In queue since April 2022 · Proposed COD January 2029
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-31
FPL-449 is a proposed solar generation project located in St. Lucie County, Florida, with a total capacity of 74.5 MW. The project, being developed by FPL, consists of 74.5 MW of solar photovoltaic generation. It is interconnected to the Florida Power & Light system at the point of interconnection named Northern St. Lucie County.
The project is currently in the Florida Reliability Coordinating Council (FRCC) interconnection queue as of April 6, 2022, with a proposed commercial operation date of January 31, 2029. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
St. Lucie
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Northern St. Lucie County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-449