FPL-452
74.5 MW generation in Indian River, FL · In queue since April 2022 · Proposed COD January 2029
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-31
FPL-452 is a proposed solar generation project with a total capacity of 74.5 MW, located in Indian River County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Power & Light utility grid at the Northern St. Lucie County point of interconnection.
The project is currently active in the Florida Reliability Coordinating Council (FRCC) interconnection queue as entry FPL-452, with a queue entry date of April 6, 2022. The proposed commercial operation date is January 31, 2029, and the project's interconnection agreement status is currently in the Facility Study phase. The project has appeared in recent news coverage regarding FPL's renewable energy expansion plans.
Generated from interconnection queue and public data sources
State
FL
County
Indian River
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Northern St. Lucie County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-452