FPL-453
74.5 MW generation in St. Lucie, FL · In queue since April 2022 · Proposed COD July 2029
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
FPL-453 is a proposed solar generation project with a total capacity of 74.5 MW, located in St. Lucie County, Florida. The project is being developed by Florida Power & Light (FPL). It consists of a single 74.5 MW solar component.
The project is currently active in the Florida Power & Light interconnection queue, with an entry date of April 6, 2022. The proposed commercial operation date is July 31, 2029, and the interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Northern St. Lucie County.
Generated from interconnection queue and public data sources
State
FL
County
St. Lucie
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Northern St. Lucie County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.