FPL-461
74.5 MW generation in Collier, FL · In queue since April 2022 · Proposed COD January 2028
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-31
The proposed project FPL-461 is a 74.5 MW solar generation project located in Collier County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Florida Power & Light system.
The project entered the interconnection queue on April 21, 2022, and has a proposed commercial operation date of January 31, 2028. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the Collier County substation.
Generated from interconnection queue and public data sources
State
FL
County
Collier
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Collier County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-461