FPL-465
74.5 MW generation in Collier, FL · In queue since April 2022 · Proposed COD January 2029
74.5 MW
Capacity
1
Components
Solar
4y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-31
FPL-465 is a proposed solar generation project with a total capacity of 74.5 MW, located in Collier County, Florida. The developer is Florida Power & Light (FPL). This project is listed in the Florida Power & Light interconnection queue as of April 21, 2022, with a proposed commercial operation date of January 31, 2029. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for FPL-465 is the Collier County substation. The project consists solely of 74.5 MW of solar photovoltaic generation. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Collier
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Collier County
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-465