FPL-467
74.5 MW generation in Okaloosa, FL · In queue since May 2022 · Proposed COD December 2024
74.5 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 7m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
FPL-467 is a proposed solar generation project located in Okaloosa County, Florida, with a total capacity of 74.5 MW. The developer and utility are both listed as Florida Power & Light (FPL). This project is currently active in the Florida Reliability Coordinating Council (FRCC) interconnection queue under queue ID FPL-467, with an entry date of May 13, 2022. The proposed commercial operation date is December 31, 2024, and the interconnection agreement status is currently in the Facility Study phase.
The point of interconnection (POI) is the Alligator Swamp - Shoal River 230 Kv substation. The project consists solely of solar photovoltaic generation, with the full 74.5 MW capacity attributed to this technology. The project has appeared in recent news coverage regarding FPL's renewable energy development plans.
Generated from interconnection queue and public data sources
State
FL
County
Okaloosa
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Alligator Swamp - Shoal River 230 Kv
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-467