Project FPL-472 — Project Summary

Queue ID
FPL-472
Capacity
74.5 MW
Technology
Solar
Status
active
Location
Desoto, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

FPL-472

FPL-472BetaActiveSolarFPLLBNL

74.5 MW generation in Desoto, FL · In queue since July 2022 · Proposed COD January 2029

74.5 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection

Total Duration

6y 6m

Facilities Study50%
Queue EntryJul 20, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-31

About

The proposed FPL-472 project is a 74.5 MW solar generation development in Desoto County, Florida. The project is being developed by Florida Power & Light (FPL) and is located within the Florida Power & Light service area. It entered the queue on July 20, 2022, and has a proposed commercial operation date of January 31, 2029.

The project's interconnection status is currently in the Facility Study phase. It is located in the Southeast region and interconnects at the Whidden Substation. The project is listed in the interconnection queue of Florida Power & Light.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

Desoto

Grid Region

Southeast

Market

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Service Type

Point of Interconnection

Whidden Sub

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project FPL-472