FPL-477
74.5 MW generation in Desoto, FL · In queue since July 2022 · Proposed COD July 2030
74.5 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
8 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-07-31
FPL-477 is a proposed solar generation project with a total capacity of 74.5 MW, located in Desoto County, Florida. The project is being developed by Florida Power & Light (FPL). It is listed as active in the Florida Reliability Coordinating Council (FRCC) interconnection queue, with an entry date of July 20, 2022, and a proposed commercial operation date of July 31, 2030. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 74.5 MW of solar photovoltaic generation. The point of interconnection is the SR70 Sweat-Whidden 230kV substation. The project has appeared in recent news coverage regarding FPL's renewable energy development plans.
Generated from interconnection queue and public data sources
State
FL
County
Desoto
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
SR70 Sweat-Whidden 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN