Project FPL-490 — Project Summary

Queue ID
FPL-490
Capacity
74.5 MW
Technology
Solar
Status
active
Location
St. Lucie, FL
Region
Southeast
Developer
FPL
IA Status
Facility Study

FPL-490

FPL-490BetaActiveSolarFPLLBNL

74.5 MW generation in St. Lucie, FL · In queue since January 2023 · Proposed COD January 2029

74.5 MW

Capacity

1

Components

Solar

3y 4m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection

Total Duration

6 years

Facilities Study50%
Queue EntryJan 6, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-31

About

FPL-490 is a proposed solar generation project located in St. Lucie County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Power & Light (FPL), is interconnected to the Florida Power & Light system in the Southeast region.

The project entered the interconnection queue on January 6, 2023, and has a proposed commercial operation date of January 31, 2029. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the Southern St Lucie County substation.

Generated from interconnection queue and public data sources

Project Details

State

FL

County

St. Lucie

Grid Region

Southeast

Market

Developer

FPL

Utility

Florida Power & Light

Entity

FPL

Service Type

Point of Interconnection

Southern St Lucie County

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
FRCC
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project FPL-490