FPL-501
74.5 MW generation in Martin, FL · In queue since January 2023 · Proposed COD April 2030
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-30
The proposed FPL-501 project is a 74.5 MW solar generation facility located in Martin County, Florida. The project, being developed by Florida Power & Light (FPL), is interconnected within the Florida Power & Light utility territory in the Southeast region.
FPL-501 entered the interconnection queue on January 6, 2023, and has a proposed commercial operation date of April 30, 2030. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is near Indiantown, Florida.
Generated from interconnection queue and public data sources
State
FL
County
Martin
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
near Indiantown
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-501