FPL-503
74.5 MW generation in Martin, FL · In queue since January 2023 · Proposed COD October 2030
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-31
FPL-503 is a proposed solar generation project with a total capacity of 74.5 MW. The development is located in Martin County, Florida, within the Southeast region, and is being pursued by Florida Power & Light (FPL). The project is currently active in the Florida Power & Light interconnection queue, with an entry date of January 6, 2023, and a proposed commercial operation date of October 31, 2030. Its interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for FPL-503 is near Indiantown, Florida. The project consists solely of solar photovoltaic generation, with the 74.5 MW capacity entirely attributed to solar components. The developer and utility are both listed as FPL.
Generated from interconnection queue and public data sources
State
FL
County
Martin
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near Indiantown
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-503