FPL-504
74.5 MW generation in Martin, FL · In queue since January 2023 · Proposed COD October 2030
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
7y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-10-31
The proposed FPL-504 project is a 74.5 MW solar generation project located in Martin County, Florida. The project, developed by Florida Power & Light (FPL), is interconnected to the Florida Power & Light system near Indiantown.
FPL-504 entered the Florida Reliability Coordinating Council (FRCC) interconnection queue on January 6, 2023, with a proposed commercial operation date of October 31, 2030. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Martin
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
near Indiantown
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-504