FPL-509
74.5 MW generation in Manatee, FL · In queue since January 2023 · Proposed COD January 2030
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-31
FPL-509 is a proposed solar generation project located in Manatee County, Florida, with a total capacity of 74.5 MW. The project, being developed by Florida Power & Light (FPL), consists of 74.5 MW of solar photovoltaic generation. It is interconnected within the Florida Power & Light system, as indicated by its queue ID.
The project entered the interconnection queue on January 6, 2023, and has a proposed commercial operation date of January 31, 2030. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is located near Myakka City.
Generated from interconnection queue and public data sources
State
FL
County
Manatee
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near Myakka City
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-509