FPL-511
74.5 MW generation in Manatee, FL · In queue since January 2023 · Proposed COD July 2033
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Facility Study
IA Status
COD target: 2033
Total Duration
10y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-07-31
FPL-511 is a proposed solar generation project located in Manatee County, Florida, with a total capacity of 74.5 MW. The project, developed by Florida Power & Light (FPL), is interconnected near Myakka City. It is currently in the Florida Power & Light (FPL) interconnection queue with an entry date of January 6, 2023.
The proposed commercial operation date (COD) for FPL-511 is July 31, 2033. The project's interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
FL
County
Manatee
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near Myakka City
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-511