FPL-513
74.5 MW generation in Charlotte, FL · In queue since January 2023 · Proposed COD January 2030
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-31
FPL-513 is a proposed solar generation project located in Charlotte County, Florida, with a total capacity of 74.5 MW. The project, being developed by Florida Power & Light (FPL), consists of 74.5 MW of solar photovoltaic generation. It is currently in the Florida Power & Light (FPL) interconnection queue with an entry date of January 6, 2023. The proposed commercial operation date is January 31, 2030, and the project's interconnection status is currently in the System Impact Study phase.
The point of interconnection for the project is near Bermont, Florida. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
FL
County
Charlotte
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near Bermont
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-513