FPL-519
74.5 MW generation in Charlotte, FL · In queue since January 2023 · Proposed COD October 2031
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
8y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-10-31
FPL-519 is a proposed solar generation project located in Charlotte County, Florida, with a total capacity of 74.5 MW. The project, being developed by FPL, consists of 74.5 MW of solar photovoltaic generation. It is interconnected to Florida Power & Light's system near Bermont.
The project is currently in the Florida Reliability Coordinating Council (FRCC) interconnection queue under queue ID FPL-519, with an entry date of January 6, 2023. Its proposed commercial operation date is October 31, 2031, and its interconnection status is currently in the System Impact Study phase. The project has appeared in recent news coverage regarding FPL's renewable energy development plans.
Generated from interconnection queue and public data sources
State
FL
County
Charlotte
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near Bermont
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-519