FPL-523
74.5 MW generation in Hendry, FL · In queue since January 2023 · Proposed COD July 2029
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
6y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-31
The proposed project FPL-523 is a 74.5 MW solar generation project located in Hendry County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Florida Power & Light system near LaBelle.
The project is currently in the Florida Reliability Coordinating Council (FRCC) interconnection queue with an entry date of January 6, 2023. Its interconnection status is System Impact Study, and the proposed commercial operation date is July 31, 2029.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near LaBelle
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-523