FPL-531
74.5 MW generation in Hendry, FL · In queue since January 2023 · Proposed COD January 2031
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
8 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-01-31
FPL-531 is a proposed 74.5 MW solar generation project located in Hendry County, Florida. The development project, under the purview of Florida Power & Light (FPL), entered the Florida Reliability Coordinating Council (FRCC) interconnection queue on January 6, 2023. The current interconnection status is System Impact Study, with a proposed commercial operation date of January 31, 2031.
The project, located near LaBelle, Florida, consists of 74.5 MW of solar photovoltaic generation. The developer and entity responsible for the project is FPL. The project has appeared in recent news coverage regarding FPL's renewable energy expansion plans.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near LaBelle
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-531