FPL-536
74.5 MW generation in Hendry, FL · In queue since January 2023 · Proposed COD July 2031
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-07-31
FPL-536 is a proposed solar generation project with a total capacity of 74.5 MW located in Hendry County, Florida. The developer is Florida Power & Light (FPL). The project is in the Florida Power & Light interconnection queue (FPL-536) with an entry date of January 6, 2023. The proposed commercial operation date is July 31, 2031.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is near LaBelle, Florida. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near LaBelle
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-536