FPL-538
74.5 MW generation in Hendry, FL · In queue since January 2023 · Proposed COD January 2032
74.5 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
9 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-01-31
FPL-538 is a proposed solar generation project with a total capacity of 74.5 MW, located in Hendry County, Florida. The project is being developed by Florida Power & Light (FPL) and is interconnected to the Florida Power & Light system near LaBelle. It entered the interconnection queue on January 6, 2023, and has a proposed commercial operation date of January 31, 2032. The project's interconnection status is currently in the System Impact Study phase.
The proposed project consists of 74.5 MW of solar photovoltaic generation. It is listed in the interconnection queue of the regional transmission organization (RTO) in the Southeast. Recent news coverage has discussed the project's potential impact on the local energy grid.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Near LaBelle
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project FPL-538