FPL-557
74.9 MW generation in Bradford, FL · In queue since February 2023 · Proposed COD January 2031
74.9 MW
Capacity
1
Components
Solar
3y 3m
In Queue
Facility Study
IA Status
COD target: 2031
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-01-17
FPL-557 is a proposed solar generation project located in Bradford County, Florida, with a total capacity of 74.9 MW. The project, developed by a third party, is interconnected with Florida Power & Light (FPL) at the Baldwin-Starke 115kV point of interconnection. It entered the FPL interconnection queue on February 23, 2023, and has a proposed commercial operation date of January 17, 2031. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 74.9 MW of solar photovoltaic generation. It is listed as active within the interconnection queue. The project has appeared in recent news coverage regarding renewable energy development in Florida.
Generated from interconnection queue and public data sources
State
FL
County
Bradford
Grid Region
Southeast
Market
—
Developer
Third Party
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
Baldwin-Starke 115kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN