FPL-563
74.5 MW generation in Hendry, FL · In queue since July 2023 · Proposed COD July 2030
74.5 MW
Capacity
1
Components
Solar
2y 10m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-07-31
The proposed FPL-563 project is a 74.5 MW solar generation project located in Hendry County, Florida. The developer is Florida Power & Light (FPL). It is interconnected to the Florida Power & Light system at the point of interconnection named State Road 80.
The project entered the Florida Power & Light interconnection queue on July 25, 2023, with a proposed commercial operation date of July 31, 2030. Its interconnection status is currently in the System Impact Study phase. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Hendry
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
State Road 80
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.