FPL-566
74.5 MW generation in Collier, FL · In queue since July 2023 · Proposed COD July 2032
74.5 MW
Capacity
1
Components
Solar
2y 10m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
9 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-07-31
FPL-566 is a proposed solar generation project located in Collier County, Florida, with a total capacity of 74.5 MW. The project, developed by FPL, is interconnected to the Florida Power & Light system. It entered the interconnection queue on July 25, 2023, and has a proposed commercial operation date of July 31, 2032. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection for the project is at State Road 80. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Collier
Grid Region
Southeast
Market
—
Developer
FPL
Utility
Florida Power & Light
Entity
FPL
Service Type
—
Point of Interconnection
State Road 80
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN