120 MW hybrid in Grant, WA · In queue since September 2017
120 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Commercial operation date not yet determined
GrantPUD-1 is a proposed 120 MW hybrid solar and battery project located in Grant County, Washington. The project, developed by Grant County Public Utility District (GrantPUD), consists of 120 MW of solar generation.
The project is in the GrantPUD interconnection queue, having entered the queue on September 1, 2017. The interconnection agreement has been executed for the project. The point of interconnection is the Rocky Ford - Larson 115kV or 230 kV line.
Generated from interconnection queue and public data sources
State
WA
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Grant County Public Utility District
Entity
GrantPUD
Service Type
—
Point of Interconnection
Rocky Ford - Larson 115kV or 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project GrantPUD-1