GrantPUD-9
300 MW hybrid in Grant, WA · In queue since September 2023
300 MW
Capacity
1
Components
Solar
2y 8m
In Queue
In Progress (unknown study)
IA Status
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
GrantPUD-9 is a proposed 300 MW solar and battery hybrid project located in Grant County, Washington. The development project, under the purview of Grant County Public Utility District (GrantPUD), consists of 300 MW of solar generation capacity.
The project is currently active in the GrantPUD interconnection queue, with an entry date of September 22, 2023. Its interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Potholes-Sand Dunes 230 kV line.
Generated from interconnection queue and public data sources
State
WA
County
Grant
Grid Region
Mountain West
Market
—
Developer
—
Utility
Grant County Public Utility District
Entity
GrantPUD
Service Type
—
Point of Interconnection
Potholes-Sand Dunes 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project GrantPUD-9