Oakhurst Solar Farm
200 MW hybrid in Mitchell, GA · In queue since April 2017 · Proposed COD December 2021
200 MW
Capacity
1
Components
Solar
9y 1m
In Queue
Facility Study
IA Status
COD target: 2021
Total Duration
4y 8m
Schedule
54 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-01
The Oakhurst Solar Farm is a proposed 200 MW solar and battery hybrid project located in Mitchell County, Georgia. The project, developed by an unknown entity, consists of 200 MW of solar generation capacity. It is interconnected to the Georgia Transmission (GTC) system under queue ID GTC-GI-100.
The project entered the GTC interconnection queue on April 19, 2017, with a proposed commercial operation date of December 1, 2021. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the Raccoon Creek 230kV Substation. The Oakhurst Solar Farm has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
GA
County
Mitchell
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Raccoon Creek 230kV Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.