Dawson Solar
150 MW generation in Terrell, GA · In queue since September 2019 · Proposed COD December 2022
150 MW
Capacity
1
Components
Solar
6y 8m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
The proposed Dawson Solar project is a 150 MW solar generation facility located in Terrell County, Georgia. The project is being developed within the Georgia Transmission (GTC) interconnection queue as project GTC-GI-122. Its queue entry date is September 2, 2019, with a proposed commercial operation date of December 1, 2022. The project's interconnection status is currently in the Facility Study phase.
The Dawson Solar project has been the subject of recent news coverage, with five articles published across industry and hazard-related categories.
Generated from interconnection queue and public data sources
State
GA
County
Terrell
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Dawson - Greenhouse Rd 115 KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN