All Star Solar
95 MW generation in Appling, GA · In queue since October 2019 · Proposed COD December 2023
95 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Facility Study
IA Status
COD target: 2023
Total Duration
4y 2m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
All Star Solar is a proposed 95 MW solar generation project located in Appling County, Georgia. The project is being developed within the Georgia Transmission (GTC) service area and is interconnected to the Pine Grove 115 kV Substation. It entered the GTC interconnection queue (GTC-GI-124) on October 4, 2019, and has a proposed commercial operation date of December 31, 2023. The project's interconnection status is currently in the Facility Study phase.
The All Star Solar project has been the subject of recent news coverage, with five articles published across regulatory, grid, and industry categories.
Generated from interconnection queue and public data sources
State
GA
County
Appling
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Pine Grove 115 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.