Union City Storage II
100 MW storage in Fulton, GA · In queue since December 2019 · Proposed COD November 2022
100 MW
Capacity
1
Components
Battery
6y 5m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
2y 11m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-11-30
Union City Storage II is a proposed 100 MW battery storage project located in Fulton County, Georgia. The project is in the Georgia Transmission (GTC) interconnection queue (GTC-GI-133) with a queue entry date of December 11, 2019. The proposed commercial operation date is November 30, 2022. The project's interconnection status is currently in the Facility Study phase, and it would connect to the Union City substation.
The development has been covered in recent news, with eight articles categorized as relating to the grid (5 articles), regulatory matters (2 articles), and the energy industry (1 article).
Generated from interconnection queue and public data sources
State
GA
County
Fulton
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Union City substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Union City Storage II