RV Solar
100 MW generation in Tattnall, GA · In queue since February 2020 · Proposed COD November 2022
100 MW
Capacity
1
Components
Solar
6y 3m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
2y 9m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-11-30
The RV Solar project is a proposed 100 MW solar generation project located in Tattnall County, Georgia. The project is in the Georgia Transmission (GTC) interconnection queue, identified as GTC-GI-136, with a queue entry date of February 23, 2020. The proposed commercial operation date is November 30, 2022. Its interconnection status is currently in the Facility Study phase.
The RV Solar project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
GA
County
Tattnall
Grid Region
Southeast
Market
—
Developer
—
Utility
Georgia Transmission
Entity
GTC
Service Type
—
Point of Interconnection
Claxton-Ludowici Primary 115 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26